Waterford Airport has lodged two significant planning applications that provide the clearest picture yet of how the airport intends to develop beyond its ongoing runway extension project. The applications, submitted to Waterford City & County Council, seek permission for a substantial expansion of the existing terminal complex and the construction of a major new hangar precinct that would significantly increase the airport’s operational and commercial capacity.
While much of the public discussion around Waterford Airport in recent years has centred on the €30 million runway redevelopment currently underway, the newly published planning documents reveal a broader vision for the airport’s future, encompassing commercial passenger operations, business aviation, aircraft maintenance and aviation-related industry.
Terminal Expansion Plans
The first application seeks permission for a two-storey extension measuring approximately 3,672 square metres to the sides and rear of the existing terminal building. According to the planning documentation, the enlarged facility would provide dedicated arrivals and departures areas together with a range of passenger amenities designed to support future scheduled airline operations.
The proposed development includes:
- Arrivals and departures facilities
- Fixed Base Operator (FBO) facilities for business aviation
- Food and beverage outlets
- A duty-free shop
- Coffee shop and canteen facilities
- Office accommodation
- Exhibition space
- Ancillary storage and plant rooms
The plans also provide for alterations to the façade and roof of the existing terminal building, creating a more modern and integrated passenger facility. In aviation terms, the inclusion of dedicated Fixed Base Operator facilities is particularly noteworthy. FBO services typically cater for corporate and private aviation, suggesting the airport is planning to develop multiple revenue streams rather than relying solely on scheduled passenger traffic.

Airport Fire Service Upgrade
As part of the same application, Waterford Airport is seeking permission for a 416 square metre, two-storey extension to the existing airport fire station. The proposed addition would include an extra fire engine bay, staff changing and locker facilities, and associated plant rooms.
The investment in airport rescue and firefighting infrastructure is significant because fire service capability is a key factor in determining the categories of aircraft an airport can accommodate. As Waterford prepares for larger commercial aircraft following completion of the runway extension, enhanced emergency response facilities will be an important part of future operations.
New Hangar Complex
The second planning application is arguably even more ambitious. It proposes the construction of eight hangar units with a combined floor area of approximately 16,553 square metres, together with integrated office accommodation and supporting infrastructure.
The development would include:
- Eight new hangar buildings
- Integrated office facilities
- Aircraft parking apron connections
- Additional car parking
- Bicycle parking facilities
- Security fencing
- Bin storage facilities
- Two ESB substations
- Aircraft set-down and circulation areas
The proposal also includes the demolition of an existing hangar building to facilitate the new layout.
While the planning applications do not identify future tenants, the scale of the hangar development suggests the airport is positioning itself to attract aviation businesses such as maintenance organisations, aircraft operators, business aviation providers and other aerospace-related enterprises. The airport has long been promoted as a strategic aviation and business hub for the South East region.
Supporting Infrastructure
Both applications include a range of supporting works that indicate a comprehensive development approach rather than standalone building projects. These include new wayfinding signage, security infrastructure, expanded car parking, cycle shelters, standalone ESB substations, landscaping and associated site works. A car rental office cabin is also proposed within the terminal development application.
Importantly, Natura Impact Statements (NIS) have been submitted with both applications, reflecting the environmental assessments required due to the airport’s proximity to protected habitats and designated conservation sites.
A Wider Vision for Waterford Airport
The applications arrive just months after construction commenced on the airport’s long-awaited runway redevelopment project. That project will extend the runway to 2,287 metres and widen it to 45 metres, allowing Waterford Airport to accommodate larger commercial jet aircraft and paving the way for the return of scheduled passenger services.
Viewed alongside the runway project, these latest planning applications provide perhaps the most detailed insight yet into the airport’s long-term ambitions. Rather than simply restoring airline services, the plans point towards the development of a multi-purpose aviation hub capable of supporting commercial passenger operations, business aviation, aircraft maintenance and aviation-related commercial activity.
If approved, the developments would represent one of the largest expansions of airport infrastructure ever undertaken in the South East and could substantially reshape Waterford Airport’s role within Ireland’s regional aviation network over the coming years.